SurePods Streamlining Healthcare Construction at AdventHealth Minneola Hospital

Hear from Thomas Kaptur, SurePods Project Manager for the Minneola Project, on how we successfully delivered all 80 pods for this facility in just 4 days. SurePods engaged early in the design phase to assist with BIM coordination, mockups, and fixture selection. Pods were staged before the building's exterior was completed, allowing other trades to continue work efficiently. Detailed planning ensured proper MEP connections and unobstructed installation paths. Each pod was placed in designated depressions with pre-coordinated templates, optimizing workflow and minimizing on-site adjustments.